Since the plant uses high-tech machinery and a large scale conveyor system, a number of services were required to carry out this project. This involved using HV contractors to commission the high voltage network on site, data contractors to install the communications system, and a team of up to 40 electricians who supplied and installed the necessary light, power, sub mains and associated switchboards.

In an effort to improve the processing plant’s’ efficiency, the design of the overhead cable tray was changed. By doing so, it supplied switchboards in the warehouse to an underground conduit network, thereby saving time on cable installation. Thus, the project was completed well within the timeframe.